Environmental Permits in Mexico

Environmental Permits Registry · Jurisdiction Record

Environmental permits in Mexico operate through a federal, state and municipal framework. At federal level, the Secretaría de Medio Ambiente y Recursos Naturales (SEMARNAT) administers environmental impact authorisations, forest-land change authorisations, hazardous waste and certain operating environmental procedures. State and municipal authorities administer many local environmental, land-use, construction, water, waste, air and operating approvals. The project’s sector, location, federal jurisdiction, environmental effects and state or municipal context determine the applicable permit portfolio.

The central development-stage environmental approval is the authorisation in environmental impact matters. Under the General Law of Ecological Balance and Environmental Protection (LGEEPA), environmental impact assessment is the procedure through which SEMARNAT establishes the conditions for works and activities that may cause ecological imbalance or exceed applicable environmental limits. The proponent submits a Manifestación de Impacto Ambiental (MIA) or, where applicable, a preventive report. SEMARNAT may authorise the project, authorise it subject to mitigation or compensation conditions, or deny authorisation.

For operating facilities, environmental obligations can include the Single Environmental Licence (Licencia Ambiental Única) for establishments within federal air-pollution jurisdiction, Annual Operating Certificate reporting, hazardous waste registration or authorisation, water concessions and discharge permits, and sector-specific environmental authorisations. The exact operating route depends on whether the facility falls under federal or state jurisdiction and on its emissions, wastewater, waste, hazardous materials, energy, mining, forest, coastal or other regulated characteristics.

For international businesses, Mexico should be treated as a multi-level permitting environment. Environmental impact authorisation, operating licences and sectoral permits must be sequenced with land, zoning, municipal construction, water, waste, forest, wildlife, energy, mining, port, coastal, industrial and local approvals. A federal SEMARNAT authorisation does not automatically replace state or municipal environmental and development requirements.

Environmental Permits Registry
└── Jurisdictions
    └── Mexico
        └── Environmental Permits
            ├── LGEEPA Environmental Framework
            ├── Environmental Impact Authorisation
            ├── Manifestación de Impacto Ambiental (MIA)
            ├── Federal, State and Municipal Allocation
            └── Operating Licences, Monitoring and Change Control

Identity

Mexico Environmental Regulation MIA / Environmental Authorisation

Object: Environmental Permits

Object Type: Regulatory Approval Function

Primary Authorities

  • SEMARNAT
  • DGIRA
  • PROFEPA
  • CONAGUA
  • State and municipal environmental authorities

Core Outcome

An environmental impact authorisation, preventive report outcome, operating licence, water or discharge permit, hazardous waste authorisation, amendment, renewal, refusal or related decision defining conditions for project development and operation.

Object Definition

Environmental permitting in Mexico is the regulatory approval and compliance function through which projects, facilities and activities with potential environmental effects are assessed, authorised, licensed, permitted and controlled. It includes environmental impact authorisation, preventive reports, operating environmental licences, air emissions, water and wastewater, hazardous waste, forest, wildlife, coastal, energy, mining, monitoring, reporting, inspection and material-change requirements.

DefinitionThe regulatory approval and compliance function for projects, facilities and activities requiring environmental impact authorisation, operating environmental licence, water, waste, forest, wildlife or another environmental decision in Mexico.
ObjectEnvironmental Permits
Object TypeEnvironmental Regulatory Approval and Compliance Function
ClassificationEnvironmental Law — Environmental Impact Assessment — MIA — Environmental Authorisation — Federal and State Administration — Industrial Emissions
JurisdictionMexico, with federal, state, municipal, regional and cross-border relevance where applicable

Object Characteristics

These characteristics describe the general operating profile of environmental permitting as a registry object in Mexico. They are classificatory indicators rather than case-specific legal conclusions; the applicable permit, authority and evidence requirements depend on federal or state jurisdiction, project type, sector, environmental effects, location, water, waste, forest, wildlife, coastal context and connected approvals.

Market MaturityHigh. Environmental impact authorisation, operating licences, water, waste, forest, wildlife and sectoral environmental approvals are established components of Mexican industrial, energy, mining, infrastructure, development, water, waste and manufacturing regulation.
Evidence StrengthHigh. Environmental authorisation and operating procedures require project, site, technical, emissions, wastewater, waste, risk, forest, biodiversity, mitigation, monitoring and environmental-management information.
Standardisation LevelModerate. LGEEPA and federal regulations establish core national frameworks, while state, municipal and sectoral regimes create substantial location- and project-specific variation.
Cross-Border IntensityVery high. United States border-region activity, international investment, ports, Gulf and Pacific marine environments, transboundary waters, energy, mining, manufacturing and supply chains can be material.
Commercial ComplexityVery high. MIA, federal versus state jurisdiction, operating licences, water, waste, forest, wildlife, coastal, energy, mining, municipal construction and local approvals can materially affect project timing and operations.

Scope

The Registry Object covers the general Mexican environmental-permit architecture, including environmental impact authorisation, MIA, preventive reports, federal and state environmental allocation, operating environmental licences, emissions, water, waste, forest, wildlife, monitoring, inspection and changes. It focuses on the distinction between project development approval and operating environmental compliance.

Covered MattersEnvironmental impact authorisation; Manifestación de Impacto Ambiental; preventive reports; environmental operating licences; air emissions; wastewater; water concessions; discharge permits; hazardous waste; forest land-use change; wildlife; coastal and marine activities; monitoring; reporting; inspection and changes.
Functional BoundaryThe object explains environmental permitting as a regulatory function. It does not replace project-specific Mexican federal, state, municipal, legal, technical, land, water, waste, forest, wildlife, energy, mining, coastal, port, safety, tax or engineering analysis.
Related but Not PrimaryLand title, zoning, municipal construction permit, water concession, groundwater, waste transport, forest clearance, wildlife permit, protected natural areas, mining concession, energy permit, port, coastal, customs, labour, safety and sectoral approvals may be connected but require separate analysis.
Outside ScopeGeneric sustainability reporting, voluntary ESG programmes and environmental claims without a direct MIA, environmental impact authorisation, operating licence, water, waste, forest, wildlife or environmental compliance question.

Purpose and Primary Outcome

The purpose of Mexican environmental permitting is to establish environmental conditions before projects and activities proceed and to control pollution and environmental effects during operation. Environmental impact authorisation determines whether a proposed work or activity may be carried out and can impose prevention, mitigation or compensation conditions. Operating permits and licences regulate emissions, waste, wastewater and continuing compliance for facilities in the applicable jurisdiction.

PurposeTo protect the environment and ecosystems through environmental impact assessment, prior authorisation, pollution control, operating licences, conditions, monitoring, inspection and enforcement.
Primary OutcomeAn environmental impact authorisation, preventive report outcome, operating environmental licence, water or discharge permit, waste, forest or wildlife authorisation, amendment, renewal, refusal or other decision.
Business ValueEarly federal, state and municipal mapping supports site selection, project feasibility, design, construction, industrial licensing, operating compliance and long-term risk management.

Request Contexts, Users and Scenarios

Environmental permit work is commonly triggered by a new industrial facility, infrastructure project, energy development, mine, water or waste project, forest land-use change, coastal development, manufacturing expansion, hazardous activity, site acquisition or material modification. The initial questions are whether the project requires federal or state environmental impact authorisation and which operating licences, water, waste, forest, wildlife and local permits apply.

Typical UserIndustrial operators, manufacturers, energy companies, mining businesses, water and wastewater operators, waste facilities, infrastructure developers, ports and coastal businesses, construction and property developers, agricultural enterprises, investors and foreign companies operating in Mexico.
Business EventNew project, industrial facility, construction, expansion, modernisation, new emissions source, wastewater discharge, waste activity, energy or mining project, forest land-use change, coastal works, site acquisition or operational modification.
Typical ScenarioA developer submits a Manifestación de Impacto Ambiental to SEMARNAT before project development; a project with high-risk activity includes an environmental risk study; an operating facility obtains federal operating environmental licence and water or hazardous waste approvals while complying with state and municipal requirements.
Professional AssistanceTypically relevant where federal versus state jurisdiction, MIA, preventive report, high-risk activity, operating licence, air emissions, wastewater, waste, forest, wildlife, coastal, energy, mining, public consultation or permit conditions are commercially material.

Country Characteristics

Mexico’s system is distinctive because it combines a federal environmental impact authorisation framework with substantial state and municipal authority over project development, operating controls and local environmental matters. SEMARNAT evaluates environmental impact authorisations within federal jurisdiction and can authorise, conditionally authorise or deny projects. State and municipal authorities can administer separate environmental and development controls, making correct jurisdiction analysis central to project strategy.

Operational CultureMulti-level, assessment-led and condition-based, with MIA, technical review, federal and local authority allocation, public information, mitigation, monitoring, inspections and operating authorisations central to the process.
Institutional StructureSEMARNAT and DGIRA administer federal impact authorisation; PROFEPA supports environmental inspection and enforcement; CONAGUA administers national water matters; state and municipal authorities manage local environmental, land-use, construction and operating requirements.
Permit LogicWorks and activities within the relevant scope require environmental impact authorisation before implementation. Operating facilities can require environmental operating licences, water or discharge permits, hazardous waste authorisations and state or municipal permits depending on jurisdiction.
Language ExpectationSpanish is central to applications, MIA documents, authority correspondence, public consultation, permits and decisions. English source materials generally require controlled Spanish translation.

Key Authorities

Authority competence depends on project jurisdiction, environmental effects and sector. SEMARNAT is the principal federal environmental authority for impact authorisations and various operating approvals. DGIRA manages impact and risk procedures within SEMARNAT. PROFEPA conducts environmental inspection and enforcement. CONAGUA is central to national water concessions and discharge matters. State and municipal authorities administer local environmental, planning and building requirements.

Secretaría de Medio Ambiente y Recursos NaturalesSEMARNATFederal environmental authorityAdministers federal environmental policy, environmental impact authorisations, operating environmental procedures, forest, wildlife, hazardous waste and other environmental approvals within federal jurisdiction.MIA, environmental impact authorisation, preventive reports, operating authorisations, forest and wildlife procedures, environmental conditions and federal permit processes.gob.mxCentral to federal environmental assessment and operating environmental authorisations.
Directorate General of Environmental Impact and RiskDGIRAFederal environmental impact authorityAdministers receipt, evaluation and resolution of environmental impact manifests and environmental risk procedures within SEMARNAT.MIA evaluation, environmental risk assessment, environmental authorisation, online and in-person impact procedures.gob.mxCentral to federal MIA and high-risk project environmental authorisations.
Federal Attorney for Environmental ProtectionPROFEPAEnvironmental inspection and enforcement authorityConducts environmental inspection, verification, enforcement and compliance activities under federal environmental law.Inspection, compliance, enforcement, environmental audit and violation response.gob.mxRelevant to ongoing federal environmental compliance and enforcement risk.
National Water CommissionCONAGUANational water authorityAdministers national water concessions, extraction, discharge, wastewater and water-resource regulation under federal water law.Water concessions, water extraction, wastewater discharge, national waters and water-use conditions.gob.mxCentral to water-resource, discharge and wastewater permissions in federal jurisdiction.
State and Municipal Environmental AuthoritiesState and municipal competent authoritiesLocal environmental and development authoritiesAdminister state environmental impact assessment, local pollution control, land use, construction, operating licences and local environmental requirements.State MIA or environmental permits, zoning, municipal construction, local industry conditions and site-specific approvals.gob.mxRelevant to local project development, operating conditions and approvals outside federal jurisdiction.

Applicable Legislation

The General Law of Ecological Balance and Environmental Protection is the central Mexican environmental framework. It establishes environmental impact assessment and the conditions for federal authorisation of works and activities. Its EIA regulation sets procedural requirements for MIA and preventive reports. Water, waste, forest, wildlife, climate, coastal, energy, mining, state and municipal laws provide additional project-specific requirements.

General Law of Ecological Balance and Environmental Protection1988Establishes Mexico’s central environmental framework, including environmental impact assessment, pollution control, ecological balance, ecosystem protection and federal environmental authorisation.Works and activities that may cause ecological imbalance or exceed applicable environmental limits and conditions, including MIA authorisation under Article 28.EIA Regulation; waste, water, forest, wildlife, climate, coastal and sectoral environmental laws.wipo.intIn force as amended and consolidated.
Regulation of LGEEPA on Environmental Impact AssessmentCurrent frameworkRegulates federal environmental impact assessment procedure, MIA, preventive reports, public consultation, risk studies and SEMARNAT authorisation processes.Federal environmental impact authorisation applications, particular or regional MIA, preventive report and high-risk project procedures.LGEEPA; official Mexican standards; SEMARNAT administrative procedures.leap.unep.orgIn force as amended.
National Waters Law and Water FrameworkCurrent frameworkRegulates national waters, water concessions, extraction, wastewater discharge and water-resource management.Water concessions, extraction, wastewater discharge, national water bodies and water-use conditions.LGEEPA; CONAGUA procedures; state water and municipal drainage requirements.gob.mxIn force as amended.
General Law for Prevention and Comprehensive Management of WasteCurrent frameworkRegulates waste prevention, management, hazardous waste, waste generators, treatment, transport and disposal requirements.Hazardous waste generation, storage, treatment, transport, disposal and related federal or local waste authorisations.LGEEPA; hazardous waste regulations; state and municipal waste requirements.gob.mxIn force as amended.

Process Flow and Decision Tree

The Mexican route begins with jurisdiction and project screening. The proponent identifies whether the project falls within federal environmental impact jurisdiction or a state or municipal route. If federal authorisation is required, the proponent prepares MIA or preventive report and submits it to SEMARNAT. The authority reviews the file and may authorise, conditionally authorise or deny the project. The operator then obtains the relevant air, water, waste, forest, wildlife and local operating approvals.

1. Define the Project and FacilityIdentify the site, proponent, operator, state and municipality, project type, capacity, construction, process, emissions, wastewater, waste, water, forest, wildlife, coastal context and intended changes.
2. Identify Federal or State JurisdictionAssess whether the project requires SEMARNAT federal environmental impact authorisation or state or municipal environmental and development approvals.
3. Determine Environmental Impact RouteDetermine whether a Manifestación de Impacto Ambiental, preventive report, environmental risk study or another assessment route applies.
4. Map Connected ApprovalsIdentify operating environmental licence, water concession, discharge permit, hazardous waste, forest land-use change, wildlife, coastal, land, construction, energy, mining and sectoral approvals.
5. Prepare the Evidence BasePrepare MIA or preventive report, technical descriptions, site plans, emissions and wastewater data, waste material, risk study, forest and biodiversity information, mitigation, monitoring and environmental management plans.
6. Submit the ApplicationSubmit federal MIA or preventive report through SEMARNAT electronic or contact-centre processes, or submit state or municipal applications to the competent local authority.
7. Examination and ParticipationThe authority reviews completeness, evaluates environmental effects, may request supplementary information, conducts public consultation where applicable and considers technical and legal requirements.
8. Decision and ConditionsSEMARNAT or the competent authority authorises, conditionally authorises, declines, amends or renews the environmental impact authorisation or related permit and establishes conditions.
9. Construct, Operate and Manage ChangeImplement mitigation and environmental conditions, obtain operating permits, monitor compliance, respond to inspections and assess changes before expansion, modification or project alteration.
Decision logic: Determine federal, state and municipal jurisdiction first. Then identify MIA or preventive-report route and map all water, waste, forest, wildlife, operating, construction and sectoral permits. The project record must align the actual facility, environmental effects, mitigation and operating conditions across all applications.

Timeline

Environmental permitting should be integrated into Mexican project development before land acquisition, financing, design, construction, industrial installation and operational commitments become fixed. Timing depends on federal or state jurisdiction, MIA type, risk study, public consultation, water and waste conditions, forest or wildlife requirements, authority review, operating licences and potential administrative or judicial challenge.

Early Project StageProject and site definition, federal versus state or municipal jurisdiction screening, MIA strategy, land, water, forest, wildlife and sectoral approval mapping.
Pre-Submission StageMIA or preventive report preparation, technical design, emissions and wastewater analysis, waste planning, risk study, biodiversity and forest review, mitigation and monitoring design.
Submission StageFederal environmental impact authorisation application is filed with SEMARNAT or state or municipal environmental applications are filed with the competent authority.
Examination StageCompleteness review, technical environmental assessment, supplementary information, public consultation where applicable, risk and mitigation assessment and authority coordination.
Decision StageEnvironmental impact authorisation, conditional authorisation, preventive report outcome, operating licence, water or waste permit, refusal, amendment or related decision.
Post-Decision StageConstruction, operating licence and sectoral approvals, monitoring, reporting, inspection and implementation of environmental conditions.
Change StageBefore changes to site, project scope, capacity, process, emissions, water, wastewater, waste, forest, wildlife, coastal effects or operating assumptions, assess MIA amendment, new authorisation or updated permits.

Required Documents

The required file depends on project jurisdiction and permit route. Federal environmental impact authorisation requires the corresponding MIA or preventive report. High-risk activities can require environmental risk study. Operating permits require technical information on the facility, emissions, wastewater, waste, water, pollution controls and environmental management. State and municipal procedures can have additional local requirements.

Manifestación de Impacto AmbientalAssesses project environmental impacts, alternatives, mitigation, environmental management, monitoring and relevant ecological effects.Projects requiring federal environmental impact authorisation under LGEEPA and its EIA regulation.
Preventive ReportProvides project information for environmental review where the applicable legal route allows preventive report rather than full MIA.Projects meeting conditions for preventive-report environmental impact procedure.
Environmental Risk StudyAssesses hazards, accident scenarios, environmental risks, prevention, emergency response and mitigation for highly risky activities.Projects involving highly risky activities requiring MIA and environmental risk assessment.
Project and Technical DescriptionExplains the project, facility, capacity, construction, processes, equipment, materials, fuels, energy use, operating arrangements and intended changes.MIA, operating licences, air, waste, water, forest, wildlife and sectoral environmental applications.
Emissions, Water, Waste and Hazardous Materials MaterialDescribes air emissions, wastewater, water use, discharge, waste generation and management, hazardous waste, storage, treatment systems and controls.Operating environmental licences, water or discharge permits, hazardous waste and industrial environmental compliance.
Site, Forest, Wildlife and Coastal MaterialShows property, facility layout, project footprint, environmental receptors, forest land, wildlife, protected areas, coastal or marine context and proposed mitigation.Projects involving land-use change, biodiversity, forest, wildlife, coastal, marine or protected-area effects.
Monitoring, Management and Corporate Authority MaterialSets out monitoring, reporting, environmental management, mitigation, incident response, compliance, authority to act and connected permit information.Environmental authorisations and operating permits with ongoing conditions and applications by project companies or authorised representatives.

Cross-Border Relevance

Mexican environmental permits are territorial and project-specific, but cross-border relevance is substantial due to United States border-region industry, transboundary water, Gulf and Pacific marine environments, international investment, energy, mining, ports, manufacturing and supply chains. Mexican permits and environmental authorisations must be assessed independently even where an operator holds comparable approvals elsewhere.

Foreign CompaniesForeign-owned proponents and operators are subject to the same Mexican federal, state, municipal and sectoral environmental approval requirements as domestic entities for projects located in Mexico.
Federal and State AllocationFederal, state and municipal environmental requirements can apply in parallel. The project location, sector, environmental effects and legal jurisdiction determine the approval portfolio.
Border, Marine and Water ContextUnited States border regions, transboundary rivers, Gulf and Pacific marine areas, ports, coastal zones, water scarcity and energy infrastructure can materially affect assessment and permit conditions.
Language ConsiderationsSpanish is central to MIA, permit applications, public consultation and authority decisions. English source materials generally require controlled Spanish translation.
Practical RiskAssuming that a foreign permit, corporate standard, state approval or authorisation from another Mexican jurisdiction automatically authorises the project or facility at the relevant site.

Operating Constraints, Risks and Costs

The central operational risk is incorrect jurisdiction and permit-portfolio mapping. A project can require federal MIA and authorisation, state and municipal development approvals, water permits, hazardous waste registration or authorisation, forest or wildlife permits and sectoral licences. The technical and environmental record must consistently reflect the actual project and operating configuration.

Jurisdiction RiskFederal, state and municipal authority allocation can differ by project, sector, location, environmental effect and regulated resource.
Impact Assessment RiskProjects requiring MIA or preventive report must secure the relevant environmental impact decision before implementation; high-risk activities can require environmental risk study.
Permit-Portfolio RiskEnvironmental authorisation, operating licence, water, discharge, waste, forest, wildlife, coastal, planning, construction, energy and mining approvals can each be required and are not automatically consolidated.
Evidence RiskIncomplete technical, MIA, risk, emissions, wastewater, waste, forest, wildlife, coastal, mitigation or monitoring material can lead to supplementary requests, delay, restrictive conditions or denial.
Condition RiskEnvironmental authorisations can impose project modifications, prevention, mitigation, compensation, monitoring, reporting, operational limits and future-change requirements.
Cost DriversMIA and technical studies, environmental risk assessment, water and waste analysis, forest and biodiversity work, public consultation, monitoring, mitigation, operating licence administration, legal and process management, redesign, renewal and appeal work.

FAQ

What is a Manifestación de Impacto Ambiental?A Manifestación de Impacto Ambiental is the environmental impact document submitted to SEMARNAT to obtain federal authorisation for works or activities that may cause ecological imbalance or exceed applicable environmental limits and conditions.
What can SEMARNAT decide after reviewing MIA?SEMARNAT may authorise the project as requested, authorise it subject to project modification or prevention, mitigation or compensation measures, or deny authorisation if legal, environmental or information requirements are not met.
Does environmental impact authorisation replace operating permits?No. Environmental impact authorisation is a project-development decision. Operating facilities can separately require environmental operating licences, water or discharge permits, hazardous waste authorisations and state or municipal approvals.
Who issues water-related permits in federal jurisdiction?CONAGUA administers national water concessions, extraction, discharge, wastewater and water-resource matters within the applicable federal water framework.
Can environmental authorisation be amended?Yes. Changes to project scope, location, capacity, process, emissions, water, wastewater, waste, forest, wildlife, coastal effects or operating assumptions can require amendment, new authorisation or updated operating permits.

Operational Considerations

This section records the principal operational variables that commonly determine how a Mexican environmental permitting matter is classified, documented, examined and administered. The variables are registry-oriented reference points and do not determine the outcome of an individual case.

Project and Facility DefinitionThe site, proponent, operator, state and municipality, project type, capacity, construction, process, emissions, wastewater, waste, water, forest, wildlife, coastal setting and intended changes should be described consistently throughout the record.
Federal, State and Municipal StatusThe project’s environmental effects, sector and location determine whether SEMARNAT federal authorisation, state environmental permit, municipal approval or a combination of routes applies.
Environmental Impact RouteMIA, preventive report or environmental risk study requirements must be determined before project implementation and aligned with the relevant SEMARNAT or state procedure.
Operating Permit PortfolioOperating facilities may require environmental operating licence, water concession, discharge permit, hazardous waste authorisation, forest, wildlife, air emissions, state and municipal permits.
Evidence BaseMIA, preventive report, risk study, technical descriptions, site plans, emissions and wastewater data, waste information, forest and wildlife material, mitigation, monitoring and corporate authority documents form the evidence base where relevant.
Decision ScopeEnvironmental authorisations and permits may define project scope, construction, capacity, mitigation, compensation, emissions, water, waste, forest, wildlife, monitoring, reporting, operating conditions and future-change requirements.
Change ManagementChanges to site, project, capacity, process, materials, emissions, wastewater, waste, water, forest, wildlife, coastal effects or operating assumptions may require MIA amendment, new authorisation, permit renewal or new state or municipal approval.

Jurisdictional Expert

This registry position is separate from the editorial reference content. Its availability does not affect the neutral description of environmental permitting in Mexico.

Registry Position IDRE-MX-ENV-001
Registry PositionJurisdictional Expert Environmental Permits Mexico
Registry AvailabilityOpen
Verification StatusNo verified participant currently assigned to this registry position.
CoverageMexican environmental impact authorisation, MIA, preventive reports, SEMARNAT, DGIRA, federal and state authority allocation, water, waste, forest, wildlife, operating permits, monitoring and domestic or cross-border project relevance.
Registry ReferenceEPR-MX-ENV-001-A Jurisdictional Expert Position
Contact InformationRegistry position not yet assigned.

Machine Layer

Object DNAenvironmental permits mexico SEMARNAT DGIRA LGEEPA Manifestacion Impacto Ambiental MIA preventive report environmental impact authorisation environmental risk study CONAGUA water concession discharge permit hazardous waste forest land use wildlife federal state municipal environmental permit air emissions monitoring cross-border
AI Retrieval SummaryNeutral registry object describing how environmental permits operate in Mexico, including LGEEPA, federal environmental impact authorisation, Manifestación de Impacto Ambiental, preventive reports, environmental risk studies, SEMARNAT and DGIRA authority, federal-state-municipal allocation, water, discharge, waste, forest, wildlife, operating licences, monitoring, changes and cross-border considerations.
Entity IndexMexico SEMARNAT Secretaría de Medio Ambiente y Recursos Naturales DGIRA General Law of Ecological Balance and Environmental Protection LGEEPA Manifestación de Impacto Ambiental MIA Preventive Report Environmental Impact Authorisation Environmental Risk Study PROFEPA CONAGUA Water Concession Discharge Permit Hazardous Waste Forest Wildlife